Elanco Liverpool

Various projects across the site. A major new research facility along with other refurbishments projects.

Technology

Industry Standards

Project Details

eco-i were appointed to design, supply, install and commission HVAC control systems for projects across the site including the new Denagard Facility and B21 refurbishment. Both projects included AHU controls including site wide steam systems, heat pumps, extract ventilation and pressure controls for the critical areas. The buildings meters where also monitored at the BMS. Eco-I worked along side the client to deliver their site specific requirements with relation to control panel manufacture and commissioning tasks.

Eco-i Works

Elanco Liverpool2
Elanco Liverpool3

Facility Management Benefits

The control panels are provided with local touchscreens to provide day to day management and alarm monitoring. The system provides a single point for the landlord to monitor their systems within the blocks